Construction site winterized

The laying of the installation lines is in full swing and the construction site is thus winterized

In the meantime, the installation work of the company Pernkopf & Haas is in full swing. The water distribution in the floors is already well advanced, and in the new year the electricians will begin. At the beginning of February, the underfloor heating and the floor construction are to follow.

In the meantime, Appesbacher Holzbau has completed some more work and winterized the house as far as possible, since the windows will not be delivered until the second week of February.